Donges Bay Road (Pilgrim Road to Magnolia Drive) - START DATE - June 20th
The work on Donges Bay Road includes full depth pulverization of the existing pavement, cutting out the soft spots in the sub-base, replacing and adding curb on the intersections, replacing sanitary sewer manhole chimneys, replacing broken water valve boxes, and placing new asphalt over the pulverized material.
Maple Road (Cedar Lane to Rockfield Road) - START DATE TBA
The work on Maple Road includes pulverizing the existing asphalt, cutting out the soft spots in the road base, and paving over with new asphalt.
Country Aire Drive (Bonniwell Road to Pioneer Road) - STARTED AUGUST 6TH
The work left to do on Country Aire Drive is to pour concrete curb along the road heading down the hill towards Pioneer Road. Then the road will be proofed rolled and any soft spot will be cut out. When that is complete, the asphalt pavement can be placed. Restoration will be started shortly after the asphalt is laid.